29 CFR 1926.703: Requirements for cast-in-place concrete
The official text is on the eCFR. Below: how the section is organized, the paragraphs our CHST questions are built on, and free questions to try.
Quoted from the eCFR, current as of 2026-10-14; last amended 2016-09-01.
How 29 CFR 1926.703 is organized
- (a) General requirements for formwork2 paragraphs
- (b) Shoring and reshoring14 paragraphs
- (c) Vertical slip forms9 paragraphs
- (d) Reinforcing steel2 paragraphs
- (e) Removal of formwork5 paragraphs
Paragraphs our practice questions cite most
Counted across the 9 live PassCited questions on this section: our bank, not the real exam.
“(2) Reshoring shall not be removed until the concrete being supported has attained adequate strength to support its weight and all loads in place upon it.”
“(iv) The single post shores shall be adequately braced in two mutually perpendicular directions at the splice level. Each tier shall also be diagonally braced in the same two directions.”
“(9) Adjustment of single post shores to raise formwork shall not be made after the placement of concrete.”
“(ii) Adequately braced where not encased in concrete.”
“(5) The jacks or other lifting devices shall be provided with mechanical dogs or other automatic holding devices to support the slip forms whenever failure of the power supply or lifting mechanism occurs.”
Free practice questions on 29 CFR 1926.703
Question 1
A concrete contractor has stacked single post shores in two tiers to support a deck form. During the pre-pour walkthrough, the site safety technician finds the following: the design was prepared by a qualified designer, the posts in both tiers are vertically aligned, and the splices are made so the posts cannot shift out of alignment. Bracing at the splice level exists in only one direction, and the individual tiers have no diagonal bracing. Which deficiency must be corrected before concrete is placed?
Show answer and source
Answer: D. The shores need bracing in two mutually perpendicular directions at the splice level, and each tier must also be diagonally braced in those same two directions
OSHA's concrete formwork rule, 29 CFR 1926.703(b)(8)(iv), requires tiered single post shores to be braced in two mutually perpendicular directions at the splice level, with every tier also diagonally braced in those two directions. Bracing only the top tier falls short. Removing splices or staggering posts is wrong because the rule requires splicing and vertical alignment.
On the job
A formwork foreman on a hospital tower job inspects tiered single post shores before a pour. A qualified designer prepared the layout, and the posts and splices look sound. Diagonal braces are installed in only one direction on each tier, so the foreman holds the pour. Single post shores must be braced in two mutually perpendicular directions at the splice level, and each tier must be diagonally braced in those same two directions.
Study aid, not site-specific safety advice. The official rule controls.
Answer D rests on
29 CFR 1926.703(b)(8)(iv)(opens ecfr.gov in a new tab)“The single post shores shall be adequately braced in two mutually perpendicular directions at the splice level. Each tier shall also be diagonally braced in the same two directions.”
Question 2
A contractor is using a vertical slip form to build a tall concrete core. The jacks climb on steel pipes. Above the concrete, the pipes pass through an open section where they are not encased. The foreman says the pipes were specifically designed for climbing and no bracing is needed. What is the correct response?
Show answer and source
Answer: D. The pipes must be adequately braced where they are not encased in concrete
OSHA's slip form rules require climbing rods or pipes to be specifically designed for the purpose and also adequately braced where not encased in concrete. A proper design alone is not enough. Pipe length and concrete strength are not the stated conditions for bracing.
On the job
A superintendent on a grain elevator project inspects a slip form where the jack rods are steel pipe designed for climbing. Several feet of pipe are exposed between the concrete and the deck above. Although the pipe was designed for the purpose, the superintendent has the crew install bracing there, because the pipes must also be adequately braced wherever they are not encased in concrete.
Study aid, not site-specific safety advice. The official rule controls.
Answer D rests on
29 CFR 1926.703(c)(1)(ii)(opens ecfr.gov in a new tab)“(ii) Adequately braced where not encased in concrete.”
Where it shows up in exam prep