Incident Command and NIMS questions for the ASP
ASP11 Domain 5: Emergency Preparedness and Response (5.4 Disaster response (incident command); 5.1 Emergency response plan elements). 3 free questions below. Every answer quotes and links the regulation paragraph it rests on.
Regulations covered
- FEMA, National Incident Management System, 3rd ed. (2017) National Incident Management System
Text pulled from the eCFR, current as of .
Question 1
A chemical release at a plant triggers a Unified Command at the on-scene incident command post (ICP). The county EOC has also activated, and each location has staffed a Public Information Officer (PIO). Within hours, the two PIOs are giving the media conflicting evacuation details. Which action by the PIOs best reflects how NIMS expects them to prevent this?
Show answer and source
Answer: C. Maintain close contact through pre-established Joint Information System protocols so messages stay coordinated
When the PIO position is staffed at both the ICP and a supporting EOC, the standard says the PIOs maintain close contact through pre-established JIS protocols. Independent releases are exactly what produces the inconsistent messaging, and the standard does not shift all messaging to one PIO or to the Safety Officer.
Answer C rests on
FEMA, National Incident Management System, 3rd ed. (2017), PDF p. 52(opens ecfr.gov in a new tab)“If the PIO position is staffed at both the ICP and a supporting EOC, the PIOs maintain close contact through pre-established JIS protocols.”
Question 2
During a warehouse chemical release response, the Incident Commander is focused on resource requests when the Safety Officer notices an entry team about to enter a zone without the required respiratory protection. The Safety Officer immediately orders the team to halt and re-equip before proceeding. Under NIMS, how should this action be characterized?
Show answer and source
Answer: B. Within the Safety Officer's role, because the Safety Officer modifies or stops the work of personnel to prevent unsafe acts
The standard states the Safety Officer modifies or stops the work of personnel to prevent unsafe acts, so halting the entry team is a proper use of that authority. The other options add approvals or limits (Operations-only authority, written IC approval, Planning revisions) that the standard does not impose.
Answer B rests on
FEMA, National Incident Management System, 3rd ed. (2017), PDF p. 80(opens ecfr.gov in a new tab)“The Safety Officer modifies or stops the work of personnel to prevent unsafe acts.”
Question 3
A wildfire-related incident at a chemical storage facility is winding down. The Logistics Section Chief notes that a fire engine from a neighboring county, sent under a mutual aid request, is no longer needed. The Planning Section Chief says the engine should simply be released immediately so the crew can drive home, and that how it is restored can be sorted out later by the home department. Which action is most consistent with NIMS guidance on demobilization?
Show answer and source
Answer: A. Planning and logistics staff collaborate before demobilization to plan how the engine is rehabilitated, replenished, or restored to operational condition
The standard says that prior to demobilization, planning and logistics staff collaborate on how resources are rehabilitated, replenished, disposed of, and/or returned or restored to operational condition. Releasing the engine with no plan ignores this step, and nothing in the standard ties release to completed reimbursement.
Answer A rests on
FEMA, National Incident Management System, 3rd ed. (2017), PDF p. 26(opens ecfr.gov in a new tab)“Prior to demobilization, incident staff responsible for the planning and logistics functions collaborate to plan how resources are rehabilitated, replenished, disposed of, and/or returned or restored to operational condition.”
20 more incident command and nims questions in the full ASP bank