Question 1

A welder on a construction site starts the day shift with an oxy-fuel cutting torch that was used and put away without incident by the night shift. Before lighting it, she opens the gas supply and hears a faint hiss and sees bubbles forming in a soap-solution test at the hose coupling nut. A coworker says the torch was fine yesterday and she can just tighten it later if the leak gets worse. What does the standard require?

Show answer and source

Answer: C. Do not use the torch because the leaking coupling is a defect found at the start-of-shift inspection; it must be repaired or replaced first

The standard requires torches in use to be inspected at the start of each shift for leaking shutoff valves, hose couplings, and tip connections, and defective torches must not be used. Yesterday's good condition does not excuse the leak, and matches are not permitted lighting devices.

Answer C rests on

29 CFR 1926.350(g)(2)(opens ecfr.gov in a new tab)
“Torches in use shall be inspected at the beginning of each working shift for leaking shutoff valves, hose couplings, and tip connections. Defective torches shall not be used.”

Report a problem

We re-check reported questions against the regulation and fix or remove them.

Question 2

A contractor runs oxy-fuel cutting on a two-shift schedule. The day crew inspected the oxygen and acetylene hoses at the start of their shift and found them in good condition. When the night crew arrives, the lead says the hoses were already checked that day, so they can start cutting right away. No incidents were reported during the day shift. What does the standard require?

Show answer and source

Answer: A. The night crew must inspect the hoses at the start of their own shift and remove any defective hose from service.

The standard requires hose in use to be inspected at the beginning of each working shift, so the day crew's inspection does not cover the night shift. Pressure testing is tied to a flashback or severe wear or damage, which is not the case here.

Answer A rests on

29 CFR 1926.350(f)(3)(opens ecfr.gov in a new tab)
“All hose in use, carrying acetylene, oxygen, natural or manufactured fuel gas, or any gas or substance which may ignite or enter into combustion, or be in any way harmful to employees, shall be inspected at the beginning of each working shift. Defective hose shall be removed from service.”

Report a problem

We re-check reported questions against the regulation and fix or remove them.

Question 3

A crew will keep several compressed gas cylinders inside a building overnight. The supervisor compares four possible locations. Which location complies with the standard for indoor cylinder storage?

Show answer and source

Answer: B. A marked, assigned spot in a dry, well-ventilated room, away from stairs and traffic lanes, with nothing stored overhead that could fall

The standard calls for definitely assigned places away from elevators, stairs, or gangways, where cylinders will not be knocked over or hit by passing or falling objects. The closed locker is tempting because it prevents tampering, but the standard bars keeping cylinders in unventilated enclosures such as lockers and cupboards.

Answer B rests on

29 CFR 1926.350(a)(11)(opens ecfr.gov in a new tab)
“Cylinders should be stored in definitely assigned places away from elevators, stairs, or gangways. Assigned storage places shall be located where cylinders will not be knocked over or damaged by passing or falling objects, or subject to tampering by unauthorized persons. Cylinders shall not be kept in unventilated enclosures such as lockers and cupboards.”

Report a problem

We re-check reported questions against the regulation and fix or remove them.

3 more compressed gases questions in the full ASP bank

The free 25-question diagnostic scores every ASP domain. The pass opens every question, timed practice, the AI tutor and full-length mocks.

Related topics

Original practice questions, not real exam items. PassCited is not affiliated with or endorsed by BCSP.