Aerial Lifts and Manufacturer Requirements questions for the CHST
CHST5 Domain 3: Safety Program Development, Implementation, and Sustainment (K3.5 Proper equipment use; manufacturers' manuals). 3 free questions below. Every answer quotes and links the regulation paragraph it rests on.
Regulations covered
- 29 CFR 1926.1404 Assembly/Disassembly—general requirements (applies to all assembly and disassembly operations).How this section is tested
- 29 CFR 1926.453 Aerial lifts.
Text pulled from the eCFR, current as of 2026-10-14.
Question 1
During crane disassembly, a rigger plans to choke a synthetic sling around a steel component with a sharp, unprotected corner. The sling's rated capacity is well above the component's weight. What does the standard require regarding the sling?
Show answer and source
Answer: A. The sling must be protected from abrasive, sharp or acute edges and from configurations such as distortion or localized compression that reduce its rated capacity
The standard requires synthetic slings to be protected from sharp or acute edges and from configurations that could reduce rated capacity. A margin between load and rated capacity does not excuse the lack of protection, and lifting slowly is not a permitted alternative.
Answer A rests on
29 CFR 1926.1404(r)(2)(opens ecfr.gov in a new tab)“Synthetic slings are protected from: Abrasive, sharp or acute edges, and configurations that could cause a reduction of the sling's rated capacity, such as distortion or localized compression.”
Question 2
A rigging supervisor is selecting synthetic slings for crane assembly. The site's general rigging practice sheet allows a higher temperature exposure than the sling manufacturer's literature does. Which source must be followed for the synthetic sling's use?
Show answer and source
Answer: D. The synthetic sling manufacturer's instructions, limitations, specifications and recommendations
When synthetic slings are used, the standard requires following the sling manufacturer's instructions, limitations, specifications and recommendations. A site sheet, operator judgment, or choosing the less restrictive limit does not replace that requirement.
Answer D rests on
29 CFR 1926.1404(r)(3)(opens ecfr.gov in a new tab)“When synthetic slings are used, the synthetic sling manufacturer's instructions, limitations, specifications and recommendations must be followed.”
Question 3
During crane disassembly, a qualified rigger plans to choke a synthetic round sling around a boom section that has sharp, unpadded steel corners. The boom section weighs well under the sling's rated capacity. What must the employer ensure before the lift?
Show answer and source
Answer: D. The sling is protected from the sharp edges, for example with edge protection, before the lift proceeds
The standard requires synthetic slings to be protected from abrasive, sharp or acute edges during assembly/disassembly rigging, regardless of how the load compares to rated capacity. Having a qualified rigger or inspecting afterward does not replace protecting the sling before the lift.
Answer D rests on
29 CFR 1926.1404(r)(2)(opens ecfr.gov in a new tab)“(2) Synthetic slings are protected from: Abrasive, sharp or acute edges, and configurations that could cause a reduction of the sling's rated capacity, such as distortion or localized compression.”
6 more aerial lifts and manufacturer requirements questions in the full CHST bank