Project management for safety: RACI charts and timelines

CSP written lesson, 5 min read. CSP Domain 2: Program Management

Written with AI help from the rules it covers, then fact-checked against them. Study aid, not site-specific safety advice. The official rule controls.

What you'll learn

  • Define Responsible, Accountable, Consulted and Informed
  • Build a RACI chart that has exactly one Accountable per task
  • Lay out a timeline with dependencies and find the critical path
  • Explain float and why it matters to a schedule

What this lesson covers

This lesson covers how to define roles with a RACI chart and how to build a project timeline and find its critical path. It matters because safety projects stall when nobody owns a task or the schedule ignores dependencies.

This lesson is included with a pass

Written lessons come with every CSP pass, along with the video lessons, the question bank, mocks and the tutor. $80 per exam for 6 months, or $143 for all three for 12 months.

Try the free safety management systems and leading indicators practice questions

See where you stand on the CSP

25 questions, free, no card. You get a readiness score for each CSP domain.

Keep going in your CSP course

Your CSP pass opens every question, the lessons, domain quizzes and full-length mocks.

ASP®, CSP® and CHST® are registered marks of BCSP. PassCited is not affiliated with or endorsed by BCSP.